For an organization, the following project schedule is given. Assume that all times are in days.

Task    Predecessor    Normal Time   Crash Time   Crash Cost Slope
A          None                  7                          7                      NA
B         A                          3                          3                       NA
C        A                          8                          4                       600
D        A                          4                          4                       NA
E        B                          6                          5                       600
F        C, D                     2                         2                        NA
G        E, F                     6                          6                       NA
H        F                          5                         3                       400
I         G, H                     4                         4                        NA
J         I                           2                         2                        NA

In a 3- to 4-page Microsoft Word document, address the following:

 

*Draw the AON project network using Microsoft Project, Microsoft Visio, or some other tool capable of creating such a network. Perform a critical path analysis for the network and calculate the ES, EF, LS, and LF times.

 

*Calculate the slack time for each activity.

 

*Identify the critical path.

 

*Assume that the organization will receive a $400 bonus for each day the duration of the project is shortened.

 

*The organization is also responsible for paying the crash cost associated with shortening the schedule. To maximize the net profit, identify which task you should crash and by how much.

Support your responses with examples.

Need in-text citationsand any sources need to be cited in APA format .  Also, it needs to be free of plagiarism.

 

Assignment 2 Grading Criteria Maximum Points
Created the AON project network. 10
Performed a critical path analysis for the network and calculated the ES, EF, LS, and LF times. 10
Identified the critical path through the network. 5
Calculated the slack time for each activity. 10
Identified the task you should crash to maximize the profit. 5
Identified the number of days by which you should crash this task in order to maximize your net profit. 5
Used correct spelling, grammar, and professional vocabulary. Cited all sources using APA format. 5
Total: 50

 
Looking for solution of this Assignment?

WHY CHOOSE US?

We deliver quality original papers

Our experts write quality original papers using academic databases.  

Free revisions

We offer our clients multiple free revisions just to ensure you get what you want.

Discounted prices

All our prices are discounted which makes it affordable to you. Use code FIRST15 to get your discount

100% originality

We deliver papers that are written from scratch to deliver 100% originality. Our papers are free from plagiarism and NO similarity

On-time delivery

We will deliver your paper on time even on short notice or  short deadline, overnight essay or even an urgent essay